| The
Crescent Lawn Company
The
Restoration Project
As the restoration project is at the point of
fruition it is timely to look at how we have got this far.
Below
we have published an article "New Angle on Famous Crescent Vista"
first produced in March 1957 in the Bath Weekly Chronicle, which
covers another restoration project to change the "cabbage plot" to
lawn.
Also there
is an extract from the CLC Secretary's report on the current
restoration which was given to the Society's AGM in April 2006.
NEW
ANGLE ON FAMOUS CRESCENT VISTA
Royal
Crescent is now back in the setting which it is loved by Bathonians
and visitors to the city in fact, the setting has been improved to
provide an entirely new vista.
Almost a
year has passed since the Parks Committee began "Operation
Face-lift" the beauty treatment which saw the cabbage patch" - as it
was often described during the years since the war disappear.
.In its
place has sprung up the rolling greensward which now provides the
Crescent's "front place".
The five
acres of grassland which during the war and up to last year provided
valuable food producing land, now merges into the Royal Victoria
Park.
The ha-ha,
(boundary ditch) which separates the parkland from the Crescent
front lawn has been retained.
To open up
the vista - it is indeed a magnificent view, both from the Crescent
and the park ends- the hedge which ran parallel with the park
pathway has been removed, the land in its immediate vicinity
flattened out and grass seeded.
The concrete
stanchions and wire fencing on the other side of the pathway are
also disappearing. Bathonians will recall that before the war cattle
and sheep grazed on this parkland. This feature is not being
re-introduced. The idea is that visitors to the park can enjoy this
five-acre area.
PUBLIC PRESSURE
The Royal
Crescent Field, to give it its full title, provided plots for 72
allotmenteers during the war.
At the end
of the war the "temporary" allotments remained and there was
pressure from the genral public and from sections of the City
Council, for the restoration of the green field.
But it was
not until 1956 when the Parks Committee assumed responsibility for
the allotments in the city that it was possible to evolve the scheme
which is now almost complete.
The
Committee were able to do so because it was possible to transfer the
allotment holders from Royal Crescent to the Lower Common site and
others in the city.
ALL FOR £200
During the
years there were many critical comments about the retention of the
field as a "cabbage plot" but the former Small-holdings and
Allotments Committee fought hard and successfully to retain the site
until it was satisfied that satisfactory alternatives were
available.
The total
cost of the restoration of the front approaches of the Crescent to
its former glory is in the region of £200.
Secretary's Update to RCS AGM 30th April 2006
FIRST, THE HISTORY
Exactly
15 years and 2 weeks ago I attended my first meeting of the Ha-ha
Committee which was set up to restore the ha-ha. At some point a few
years later the Railings and their footings were added to this
project but when estimates were obtained came to approximately
£100,000 we realised that finding the necessary finance would be a
huge problem.
Then in 1997, Glenn Humphreys who works for B&NES in what was the
Parks and Cemeteries department was showing the Heritage Lottery
Fund officer round the Royal Victoria Park discussing the
restoration work he hoped to carry out there, the Heritage Lottery
Fund man saw what a parlous state the ha-ha and railings were in and
suggested that they too should be added to Glenn’s schedule of
improvements. The offer was that the Heritage Lottery Fund would pay
75% towards the costs of the ha-ha and railings restoration - an
offer we could not refuse.
Two problems arose when it was discovered that the actual owner of
the lawn and its boundaries was not known, and HLF could not proceed
with their offer until an owner was found. This problem was solved
by applying to the Land Registry for Title on the Lawn and its
Boundaries that the Society and its predecessors had always acted as
if they were the owners. The second problem was that HLF would not
allow monies to go to clubs and societies. This was solved by
creating the Crescent Lawn Company Limited which was to hold the
Title on behalf of the residents of the Royal Crescent.
Things proceeded slowly but by February of last year all the
legalities between the CLC, B&NES and Heritage Lottery Fund had been
completed.
Another aspect of the restoration was to replace the tarmac of the
path around the railings with pennant stone. This was another
project that the Royal Crescent Society had been wanting to carry
out for many years and it was obvious that a good time to do it
would be whilst the railings and footings were to be disturbed.
In August of last year both a Design Consultant and a Project Lead
Monitor were appointed. The Design Consultant is Rhys Brookes of
Harrison Brookes, Architects and the Project Lead Monitor is Cliff
Barnes of Nisbet, Chartered Quantity Surveyors, who will be working
to Heritage Lottery Fund rules and standard.
Although the CLC thought that our project was the first on Glenn
Humphry’s list of 33 projects being carried out using Heritage
Lottery Funds; we were in fact the 3rd. The first project was the
replacing of the gates in the Royal Victoria Park at the east end
near the War Memorial, and also those gates at the west end. The
second was an education centre. But since February of this year Rhys
Brookes has been working exclusively on our project and has carried
out an impressive amount of work, so much so that he has already
been able to apply for Listed Building Consent for both the ha-ha
and the railings and pavement. Unfortunately Permissions can take
3-4 months to be granted and the meantime Rhys will be completing
the specification and tendering for the work. This being so, we hope
physical work will start in or about August, which still leaves
adequate time to complete the work by the end of December.
The Present and Future
Ha-ha.
English Heritage wanted the ha-ha and ditch to be left in accordance
with their “as found” policy. No one was happy with this and the
consent application contains the decision to dig out only the late
19th and 20th century levels of the ditch, restore the top course of
the wall and to replace the bricks and breezeblocks with stone. I
heard yesterday that English Heritage will agree to this.
Railings. These will be dealt with treating the worst first. This
means that replacing the double gates and restoring both ends of the
railings and footings will be the first, working towards the centre
until the money runs out. Lisa Oestreicher who is one of the leading
paint historians in the country, has completed her examination of
the paint work and is currently working on a board on which to
display them. She has found grey, racing green and chocolate brown.
However any change from the present black may well lead to delay and
it would have to have Consent.
Pavement. The tarmac will have to be removed before the railings and
footings can be worked on, and will be re-laid with re-cycled stone
only after the railings and footings have been completed. The stone
pavement will extend from the present position at the east end up to
the point where there is a change of design of railings at the west
end. I should remind you that financing the pavement does not come
under the Heritage Lottery Funds umbrella, and fund raising will
have to take place.
|